DWR Structure

Traditionally, construction companies include information in their logs that makes sense within the contractual context they wish to monitor. However, it must be considered that the DWR (Daily Work Report) also needs to be aligned with the Construction Order Book. This, in turn, follows a structure defined by the resolutions of the Federal Council of Engineering and Agronomy / CONFEA, such as Resolution 1094.

Thus, your DWR needs to provide an accurate picture of what is happening in the project, but this view must be in harmony with the contract and current legislation.

See below the sections, which we call channels at RDOWEB, that a good DWR should contain.

Cover or Header

Identifies stakeholders, the project description or scope, contractual deadlines, responsible parties, working hours, the date, and the DWR identifier. In other words, the main information of the enterprise is recorded in this section.

Quadro de PDF na sessão de Cabeçalhos

Tasks and Activities

This channel must be connected to the project planning. You achieve this by pre-loading a list of activities coming from the Work Breakdown Structure (WBS) or the project schedule. It is not necessary to load the entire WBS of the project; you can use a level 1 or 2 grouping to make it leaner.


Thus, the person will record what was performed by selecting tasks from a predefined list. After that, they can add complementary remarks, attach photos, and record progress (quantities performed).

Quadro de PDF na sessão de Tarefas e Atividades

Weather Conditions

In this channel, you must record the general weather conditions that occurred at your project site. Keep in mind we are not just talking about rain here. In projects that work with cranes, for example, wind can be a determining factor. Others, such as piers, need to monitor tide tables.


Although recording it is relatively simple, remember that it is an uncontrollable and sometimes highly impactful variable. Therefore, always use data from a reliable source, such as the National Institute of Meteorology (INMET), an owned weather station, or at least a correctly installed bubble rain gauge on site.

Gráfico de precipitação por mês

Occurrences and Relevant Facts

Communication between parties occurs through this channel. Field occurrences and any events (whether impactful to the project or not) are recorded here. Replies and counter-replies from inspectors or the end client will also be stored here, sequentially ordered like a conversation on a timeline.


Many people use this channel to describe only minor events to avoid controversial topics, fearing that communication might turn into a 'flamewar'. This, however, can be avoided simply by adopting a neutral writing style, avoiding emotions and describing only what happened objectively.

Quadro de PDF na sessão de Fatos Relevantes

Labor / Workforce

The workforce chart, when well recorded, provides plenty of valuable information about labor costs, estimates, punctuality, safety, and project compliance. It is also possible to infer productivity rates by cross-referencing information from here with the activity channel.


However, accurately recording this data can be time-consuming and intensive. To solve this issue, RDOWEB integrates with turnstiles and time clocks, gathering data automatically. If your project does not have turnstiles, you can still batch upload information by importing data from previous DWRs or Excel spreadsheets.

Quadro de PDF na sessão de Quadro de Efetivo

Equipment and Tools

Every log must contain a record of equipment usage throughout the day. This type of information usually helps coordinate service schedules for machines and equipment, providing a general overview of their usage in the project. More efficient usage, as well as knowing when and where it is more cost-effective to rent certain types of equipment, will depend on these records.

Quadro de PDF na sessão de Equipamentos e Ferramental

Stoppages and Downtime

Although records in this channel almost always indicate potential delays, a good DWR must include stoppage and interruption events even if they do not impact the schedule. Delays here should follow the same premises used in the project budget. For example, if the project was budgeted based on hours, you should record interruptions in full hours, avoiding reporting minutes of stoppage. Also, avoid discussing values, blame, and whether the event is billable or not, describing only what happened.

Quadro de PDF na sessão de Paralisações

Accidents

Safety must be everyone's main goal, and a good DWR must mandatorily contain information when incidents occur. Even if a separate accident report is formally submitted, you are still required to report it in your DWR. In this channel, work accidents or significant incidents that occur must be recorded, even if succinctly.

Quadro de PDF na sessão de Acidentes

Footer

Although the Daily Work Report is technically considered a record (records are valid with just one signature), it is good practice for both parties to sign each report. Some projects have also collected signatures from hired management companies, closing the document with 3 signature fields.


Here, the important thing is that the signers have power of attorney to avoid disputes.

Imagem demonstrativa de rodapé com assinaturas em um PDF
Last updated on 06/15/2026

Technical Presentation

REQUEST A DEMO

Fill in the fields and one of our specialists will get in touch to schedule the best day and time.

Find out more

CONTACT